The Most Critical Use for Project Portfolio Analysis Is To

Question 33

Multiple Choice

The most critical use for project portfolio analysis is to:


A) Compare the net value of a new project relative to continuing previously approved projects
B) Determine the best time to start a new project
C) Assess the feasibility of starting a new project relative to the resources being allocated to existing projects as well as assessing the strategic fit of the new project
D) Make room for a new project by canceling or postponing an existing project that will not produce as high an ROI as the new project