Which statement about risks is FALSE?
A) A risk that could have a positive impact on a project's objectives is known as an opportunity
B) A risk that could have a negative impact on a project's objectives is known as a threat
C) A risk that a project's product is incomplete is known as an off-specification
D) A risk is an uncertain event that, should it occur, will have an effect on a project's objectives
Correct Answer:
Verified
Q93: Which is one of the six aspects
Q94: Which is NOT a purpose of a
Q95: Which is a purpose of the Managing
Q96: Which process is used by a Team
Q97: Which product describes the roles and responsibilities
Q99: Identify the missing words in the following
Q100: Identify the missing words in the following
Q101: Which is NOT confirmed during the Initiating
Q102: What theme establishes the mechanisms to judge
Q103: Which is NOT a PRINCE2 principle?
A) Learn
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents