Which Is NOT Confirmed During the Initiating a Project Process

Question 101

Multiple Choice

Which is NOT confirmed during the Initiating a Project process?


A) How the management and specialist products of the project should be baselined
B) How the method will be tailored for the size and complexity of the project
C) Whether the expected benefits have been achieved
D) Who will make decisions on any changes during the project