In the ceiling zone method of distribution, the usable floor area should be divided into zones each measuring:
A) 9.3 sq m (100 sq ft) to 23 sq m (250 sq ft)
B) 23 sq m (250 sq ft) to 56 sq m (600 sq ft)
C) 23 sq m (250 sq ft) to 84 sq m (904 sq ft)
D) 56 sq m (600 sq ft) to 84 sq m (904 sq ft)
E) 56 sq m (600 sq ft) to 100 sq m (1,100 sq ft)
Correct Answer:
Verified
Q73: Perimeter raceway systems should be used primarily
Q74: Using the "pathway design" for horizontal cable
Q75: An existing ceiling raceway system has 115,000
Q76: When placing an optical fiber cable in
Q77: Which type of cable tray is best
Q79: Which of the following statements best describes
Q80: You are designing a horizontal distribution system
Q81: You are reviewing a building backbone design
Q82: You have been asked to design a
Q83: You have been asked to project manage
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents