You are reviewing a building backbone design with a vertically aligned telecommunications room (TR) . In the spec you note in a footnote with details that the slots at one end of the telecommunications room (TR) must be flush with the floor and the sleeves provide at the end of the telecommunications room (TR) must also be flush. In your meeting with the electrical engineering firm that has provided the spec, you make the comment that according to best practices, the MINIMUM that slots and sleeves must extend above the finished floor are:
A) 25 mm (1 in) for slots and 51 mm (2 in)
B) 25 mm (1 in) for slots and 25 mm (1 in)
C) 51 mm (2 in) for slots and 25 mm (1 in)
D) 51 mm (2 in) for slots and 51 mm (2 in)
E) 64 mm (2 1/2 in) for slots and 64 mm (2 1/2 in)
Correct Answer:
Verified
Q76: When placing an optical fiber cable in
Q77: Which type of cable tray is best
Q78: In the ceiling zone method of distribution,
Q79: Which of the following statements best describes
Q80: You are designing a horizontal distribution system
Q82: You have been asked to design a
Q83: You have been asked to project manage
Q84: When reviewing a backbone distribution system within
Q85: Rack mounted hardware is installed in two
Q86: When designing a fiber backbone using cable
Unlock this Answer For Free Now!