At the end of the second week of a project, the earned value (EV) of work is $8000 USd and the planned value (PV) of work is $7000 USd. What is true about the project?
A) The project is ahead of schedule.
B) The project is over budget.
C) The project is behind schedule.
D) The project is under budget.
Correct Answer:
Verified
Q187: What is the worst case acceptance value
Q188: What is the PERT estimate of time
Q189: Which of the following does NOT describe
Q190: What type of estimate is based on
Q191: Which is NOT true about conformance quality?
A)
Q193: Color codes for cross-connections fields have been
Q194: All of the following are considered market
Q195: Where backbone cabling exceeds cabling lengths for
Q196: When developing a safety plan, consider all
Q197: A work breakdown structure is:
A) Influenced by
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents