What is the PERT estimate of time for cable placement on a given job? - Optimistic time is 100 hours - Most likely time is 125 hours - Pessimistic time is 210 hours
A) 100 hours
B) 125 hours
C) 135 hours
D) 155 hours
E) 175 hours