Select the appropriate task to complete the section 2.2 of the work breakdown structure below: 2. Technician 2.1 Install rack 2.2 _________ 2.3 Place fiber 2.4 Terminate fiber 2.5 Test fiber
A) Prepare as-built drawings
B) Install connector housing
C) Clean/polish connectors
D) Specify fiber