You Are Preparing to Test Newly Installed Open Office Cabling

Question 186

Multiple Choice

You are preparing to test newly installed open office cabling. Within the open office cabling, there are multiple consolidation points (CP) that were installed while waiting for furniture. How do you proceed with permanent link testing?


A) Test to each CP, then test from CP to workstation.
B) Wait for open office cabling to be completed, then test to each workstation outlet, including the CP.
C) Test that the CP is within 90 meters, then test again to the workstation outlet.
D) Perform permanent link tests to each CP, then continuity tests from CP to each workstation outlet.
E) Test to each workstation outlet, treating each outlet as a channel.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents