A business analyst (BA) on a project is in the process of validating requirements and finds that there is a high degree of uncertainty related to one of the assumptions being true. The BA adds the assumption to the risk register and performs a full risk analysis to handle this situation. What type of strategy is in place if the organization is risk-averse?
A) Acceptance
B) Avoidance
C) Mitigation
D) Transfer
Correct Answer:
Verified
Q442: The solution presented by a business analyst
Q443: In a risk assessment exercise of a
Q444: A company with a big information technology
Q445: A large insurance company wants to buy
Q446: A company is in the middle of
Q448: A non-profit utility company has 900 employees,
Q449: A business analyst (BA) wants to create
Q450: A business analyst (BA) had identified redundancy
Q451: When determining the success criteria for an
Q452: A business analyst (BA) finds that the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents