You have 83 project stakeholders from all across your organization. Some of the stakeholders, such as functional management, require weekly communication from you, while other stakeholders, such as the end users, only need quarterly progress updates. Where can you record these communication requirements based on your stakeholder analysis?
A) Project schedule
B) Project scope management plan
C) Project reporting structure
D) Project communications management plan
Correct Answer:
Verified
Q287: When can changes to requirements occur in
Q288: Mark is a business analyst for his
Q289: What should an organization do if the
Q290: You are the business analyst for your
Q291: You are the business analyst for your
Q293: You are the business analyst for your
Q294: You are the business analyst for a
Q295: You work as a business analyst for
Q296: Sam is the project manager of the
Q297: As a business analyst, it's important to
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents