A project manager wants to introduce the practice of a WBS to the PMO, but the other managers believe this will create extra work. Which of the following would BEST communicate the need for a WBS to the other managers? (Choose two.)
A) Using the WBS will help prevent work from slipping or being forgotten.
B) TheWBS will be required on very large projects.
C) TheWBS will be required if the project manager has the time available to complete it.
D) TheWBS will aid in determining which resources are required for the project.
E) The WBS is the best way to determine risks of the project.
Correct Answer:
Verified
Q63: Which of the following elements should be
Q64: A company is hired to perform some
Q65: A project manager has been assigned a
Q66: A team member learns that an assigned
Q67: Which of the following roles has approval
Q69: During a project, the project manager discovers
Q70: A project team has purchased computers with
Q71: A project manager is assigned to an
Q72: Which of the following vendor documents specifically
Q73: Which of the following shows projected project
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents