A team member learns that an assigned task is not due until the very end of the project. Moreover, the team member is not aware of any predecessor tasks dependent on completing the assigned task. Which of the following does the project manager use to decide if the team member can start the task later or earlier?
A) Review the PERT chart and evaluate if the task is a critical dependency.
B) Review the PERT chart and evaluate if the task is a discretionary dependency.
C) Review the PERT chart and evaluate if the task is a real dependency.
D) Review the PERT chart and evaluate if the task is an external dependency.
Correct Answer:
Verified
Q61: A project has activities on the critical
Q62: The project manager of a global project
Q63: Which of the following elements should be
Q64: A company is hired to perform some
Q65: A project manager has been assigned a
Q67: Which of the following roles has approval
Q68: A project manager wants to introduce the
Q69: During a project, the project manager discovers
Q70: A project team has purchased computers with
Q71: A project manager is assigned to an
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents