A project has activities on the critical path that must be completed before other activities can start. Task A is dependent on Task C before Task D can be completed. Task A requires task B to start. Task B takes twice as long to complete as Task C. Which of the following is the appropriate ordering of the critical path?
A) B, A, D
B) C, B, D, A
C) D, A, C
D) B, C, A, D
Correct Answer:
Verified
Q56: A project team member highlights to the
Q57: Which of the following are examples of
Q58: A project manager has noticed poor attendance
Q59: A company has dictated project scope changes
Q60: An agreement document that is intended to
Q62: The project manager of a global project
Q63: Which of the following elements should be
Q64: A company is hired to perform some
Q65: A project manager has been assigned a
Q66: A team member learns that an assigned
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents