A Project Team Member Highlights to the Project Manager That

Question 56

Multiple Choice

A project team member highlights to the project manager that expensive licensing for critical software in use across the project may expire before the completion project. Which of the following would the project manager MOST likely do?


A) Place a risk on the risk register and arrange a risk review with the appropriate stakeholders to accept and/or mitigate the risk.
B) Raise a purchase order to purchase the licensing and ask the team member to install it.
C) Amend the project scope and raise a project change request to obtain approval of the amendment.
D) Amend the project schedule and work breakdown structures to remove the use of the software from the project.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents