A project team member highlights to the project manager that expensive licensing for critical software in use across the project may expire before the completion project. Which of the following would the project manager MOST likely do?
A) Place a risk on the risk register and arrange a risk review with the appropriate stakeholders to accept and/or mitigate the risk.
B) Raise a purchase order to purchase the licensing and ask the team member to install it.
C) Amend the project scope and raise a project change request to obtain approval of the amendment.
D) Amend the project schedule and work breakdown structures to remove the use of the software from the project.
Correct Answer:
Verified
Q51: A project has fallen behind schedule. Upon
Q52: A project manager noticed the development team
Q53: A project team is mainly based in
Q54: Which of the following describes how a
Q55: A project manager was directed to complete
Q57: Which of the following are examples of
Q58: A project manager has noticed poor attendance
Q59: A company has dictated project scope changes
Q60: An agreement document that is intended to
Q61: A project has activities on the critical
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents