A project has fallen behind schedule. Upon investigation, the project manager determines that team members have implemented requirements relayed via impromptu hallway meetings with the client. Which of the following should the project manager do to resolve this issue?
A) Update the scope management plan.
B) Modify the project baselines.
C) Implement change control management.
D) Inform the stakeholders of the issue.
Correct Answer:
Verified
Q46: A vendor is unable to deliver an
Q47: A project manager received a change request,
Q48: An authorized change to a construction project
Q49: A project manager needs to track the
Q50: A new project sponsor has joined the
Q52: A project manager noticed the development team
Q53: A project team is mainly based in
Q54: Which of the following describes how a
Q55: A project manager was directed to complete
Q56: A project team member highlights to the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents