A project manager needs to track the actual and estimated start and finish dates of all WBS work packages. Which of the following is a necessary step to record the actual durations?
A) Establish each WBS work package resource.
B) Establish and set the baseline.
C) Establish and set the quality gates.
D) Establish the tollgates.
Correct Answer:
Verified
Q44: A project manager who is part of
Q45: Due to a new government regulation, a
Q46: A vendor is unable to deliver an
Q47: A project manager received a change request,
Q48: An authorized change to a construction project
Q50: A new project sponsor has joined the
Q51: A project has fallen behind schedule. Upon
Q52: A project manager noticed the development team
Q53: A project team is mainly based in
Q54: Which of the following describes how a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents