A project manager received a change request, immediately documented the required changes, and evaluated the impact of and justification for the changes. Which of the following should the project manager do NEXT?
A) Gain approval for the changes.
B) Identify the approval authority.
C) Implement the changes.
D) Create an emergency change request.
Correct Answer:
Verified
Q42: Which of the following is a schedule
Q43: Team members have reported that meetings are
Q44: A project manager who is part of
Q45: Due to a new government regulation, a
Q46: A vendor is unable to deliver an
Q48: An authorized change to a construction project
Q49: A project manager needs to track the
Q50: A new project sponsor has joined the
Q51: A project has fallen behind schedule. Upon
Q52: A project manager noticed the development team
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents