? new stakeholder has been added to a project with a BAG of $850,000. The stakeholder has raised five change requests to the CCB; two of them have been approved, and three are awaiting initial review. Considering the project has a CPI of 0.89 and an SPI of 1.14, and the approved ones will be implemented, which of the following should the project manager do LAST?
A) Identify and document the risk.
B) Evaluate the impact and justification.
C) Implement the change.
D) Update the documents and plans.
Correct Answer:
Verified
Q84: A project team on a four-year project
Q85: A project is taking more effort than
Q86: A risk with minor impact has been
Q87: Which of the following charts is a
Q88: A team member has completed an assigned
Q90: The project schedule performance index is 1.1,
Q91: A project team has finished creating a
Q92: Which of the following would indicate a
Q93: A project manager is releasing resources and
Q94: A team has been assembled and assigned
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents