A Team Has Been Assembled and Assigned a Project to Reduce

Question 94

Multiple Choice

A team has been assembled and assigned a project to reduce recent, unanticipated production cost overruns. Which of the following tools should the project team select to determine the possible origins of the increased costs?


A) Pareto chart
B) Fishbone diagram
C) Process diagram
D) Run chart