Multiple Choice

At a weekly project team meeting, it is apparent the project is over budget. The project manager needs to determine the reason for this issue. Which of the following documents should MOST likely be analyzed to obtain the answer?


A) Project charter, organization chart, scope statement, and issue log
B) Dashboard information, action items, project schedule, and status report
C) Project management plan, scope statement, communication plan, and meeting agendas
D) Project schedule, project management plan, communication plan, and issue log