A change must be made to a project to comply with municipal code. The project manager updates the relevant shared project documents. The key stakeholders subsequently update the documents with new information. When the project deliverables are reinspected, they fail the inspection. Which of the following is the MOST likely reason for the failed inspection?
A) There were insufficient resources assigned to the task.
B) The prior document version was not reviewed.
C) Version control processes were not applied.
D) The CCB was not contacted.
Correct Answer:
Verified
Q93: A project manager is releasing resources and
Q94: A team has been assembled and assigned
Q95: A project manager has been asked to
Q96: A non-stakeholder approaches the project manager and
Q97: A project team added a new member
Q99: At a weekly project team meeting, it
Q100: An industry leader may be joining the
Q101: Which of the following is described as
Q102: Which of the following activity sequencing techniques
Q103: In a project with a ??? of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents