The business stakeholder has been engaged late and has just had a chance to review the approved requirements. Consequently, it has been identified that there are a number of gaps in the requirements which are critical to the stakeholders's business unit. Which of the following actions should the project manager take?
A) Initiate change control.
B) Follow communications plan.
C) Manage project quality.
D) Prepare a performance report.
Correct Answer:
Verified
Q103: In a project with a ??? of
Q104: The project team is not comfortable moving
Q105: A sponsor requests that the project team
Q106: A post implementation review is being performed
Q107: Which of the following risk strategies is
Q109: Task B is not planned to start
Q110: Resources for a project report to a
Q111: A project manager is trying to ensure
Q112: Which of the following techniques modifies the
Q113: The design activity of a project has
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents