A Sponsor Requests That the Project Team Shorten the Completion

Question 105

Multiple Choice

A sponsor requests that the project team shorten the completion of a project by two months to give the sales team more leverage in renegotiating the contract with the client. The budgeted time is 500 hours, and the projected earned value is $30,000. A sponsor requests that the project team shorten the completion of a project by two months to give the sales team more leverage in renegotiating the contract with the client. The budgeted time is 500 hours, and the projected earned value is $30,000.   Which of the following represents the cost variance for both project completions? A)  -$4.8K and -$7K B)  -$4.9K and $7K C)  $4.8K and -$7K D)  $4.8K and $7K Which of the following represents the cost variance for both project completions?


A) -$4.8K and -$7K
B) -$4.9K and $7K
C) $4.8K and -$7K
D) $4.8K and $7K

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents