If a Project Sponsor Wants to Know the Current Status

Question 210

Multiple Choice

If a project sponsor wants to know the current status and progress of a project, which of the following is the BEST approach to find this information?


A) The project sponsor should obtain the current status from team members, put it into a presentation, and present it to the project manager for review.
B) The scheduler should obtain the current status from team members, apply it to the baseline of the schedule, and run a report.
C) The scheduler should obtain the current status from team members, update the project charter, project management plan, dashboard, and SOW, and then create a status report to provide to the project manager.
D) The scheduler should obtain the current status from team members, update the risk register, and provide the information to the project champion for review.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents