If a project sponsor wants to know the current status and progress of a project, which of the following is the BEST approach to find this information?
A) The project sponsor should obtain the current status from team members, put it into a presentation, and present it to the project manager for review.
B) The scheduler should obtain the current status from team members, apply it to the baseline of the schedule, and run a report.
C) The scheduler should obtain the current status from team members, update the project charter, project management plan, dashboard, and SOW, and then create a status report to provide to the project manager.
D) The scheduler should obtain the current status from team members, update the risk register, and provide the information to the project champion for review.
Correct Answer:
Verified
Q205: The key stakeholders have reported the project
Q206: The client accepts the critical design review.
Q207: A customer asks a project manager if
Q208: A company decides to give a large
Q209: A project manager has an opportunity to
Q211: A program manager informs a project manager
Q212: A project manager is working on the
Q213: A project has been experiencing some difficulties
Q214: Which of the following measurements would give
Q215: A business has implemented a new online
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents