Question 211

Multiple Choice

A program manager informs a project manager that a new, high-priority project has been approved and will need the current project's resources before the scheduled project close date. The project team meets and determines that the project should be fast-tracked. Which of the following documents should the project team reference to fast-track the project? (Choose two.)


A) Scope management plan
B) Configuration management plan
C) Network diagram
D) Project schedule
E) Project plan

Correct Answer: