Question 240

Multiple Choice

A project manager is informed that a team member would like to enhance the code with an additional function. Which of the following should the project manager do NEXT?


A) Submit a change request.
B) Evaluate the impact of the change.
C) Get approval from the CCB.
D) Communicate the change to stakeholders.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge