A project manager is informed that a team member would like to enhance the code with an additional function. Which of the following should the project manager do NEXT?
A) Submit a change request.
B) Evaluate the impact of the change.
C) Get approval from the CCB.
D) Communicate the change to stakeholders.
Correct Answer:
Verified
Q235: Which of the following is a team-building
Q236: An outsourced project team member approaches the
Q237: A new high-priority project is assigned to
Q238: A governance committee has just approved a
Q239: A project has a ??? of $850,000.
Q241: A project manager is required to maintain
Q242: Which of the following activity sequencing techniques
Q243: Which of the following analyses should a
Q244: A project team is in the process
Q245: A project is coming to the end
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents