Solved

A Project Has a ??? of $850,000

Question 239

Multiple Choice

A project has a ??? of $850,000. The project manager has identified and documented that certain key applications were not included in the scope management plan. As reported, the CPI is 0.8, and the PMO allows only a 5% additional increment to the planned budget. Which of the following should the project manager do NEXT?


A) Add the required work to complete the project behind $892,500.
B) Evaluate the impact and justify adding new work to the project.
C) Obtain approval from the CCB.
D) Request a budget increase of $170,000.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents