Upon assignment to a project, the project manager is given a set budget, a due date, and a clearly defined description of desired deliverables. Which of the following should the project manager do NEXT?
A) Determine the flexibility between the project constraints
B) Hold a kick-off meeting with the project team
C) Determine procurement needs to meet the project demands
D) Create the risk register
Correct Answer:
Verified
Q312: The managing director of a law firm
Q313: A company purchased a parachute supplier and
Q314: A company was originally organized using a
Q315: The project team is moving from high-level
Q316: According to the communication management plan, the
Q318: A project team is working on a
Q319: Which of the following documents are considered
Q320: In the review of a project status
Q321: A stakeholder with whom the project manager
Q322: After SOW and contract approvals, the project
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents