A stakeholder with whom the project manager has worked on numerous occasions drops by and requests that the project management add two small items to the application under development. The stakeholder has seen the value of these changes in other applications and assures the project manager they are easy, quick changes. Which of the following BEST describes how the project manager should respond?
A) Take the request to the CCB
B) Quickly make the changes
C) Ask a project team member to make the changes
D) Inform the sponsor of the stakeholder's request
Correct Answer:
Verified
Q316: According to the communication management plan, the
Q317: Upon assignment to a project, the project
Q318: A project team is working on a
Q319: Which of the following documents are considered
Q320: In the review of a project status
Q322: After SOW and contract approvals, the project
Q323: Which of the following is the first
Q324: A project facilitator is working within a
Q325: While planning a project, the project team
Q326: A project sponsor wants to know which
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents