A project facilitator is working within a large project team that includes 36 members representing different organizational groups. The current communications plan calls for full status updates to be emailed to the whole group twice per week. Which of the following factors should be considered FIRST when communicating with this group?
A) Providing all parties with frequent updates keeps the team on the same page as the project moves forward.
B) The large team may be dispersed over different time zones, preventing the team from receiving the status updates at the same time.
C) The frequency, method, and level of detail provided should be different for each target audience.
D) All team members receive the same level of detail, ensuring the accuracy of the status updates
Correct Answer:
Verified
Q319: Which of the following documents are considered
Q320: In the review of a project status
Q321: A stakeholder with whom the project manager
Q322: After SOW and contract approvals, the project
Q323: Which of the following is the first
Q325: While planning a project, the project team
Q326: A project sponsor wants to know which
Q327: Which of the following project roles is
Q328: An organization is divided into three separate
Q329: A stakeholder wants to add four more
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents