A financial audit is being performed on a closed project. Which of the following should be communicated with FIRST?
A) Stakeholders
B) Project management office
C) Functional managers
D) Quality control
Correct Answer:
Verified
Q328: An organization is divided into three separate
Q329: A stakeholder wants to add four more
Q330: A project sponsor approved an undocumented change
Q331: A project manager has updated the risk
Q332: Midway through a project, the building the
Q334: A project team has just finished one
Q335: A project manager is implementing a new
Q336: A project manager is planning to hold
Q337: A customer is in the early planning
Q338: The PMO has asked the PM to