A project manager has updated the risk register with the current risk status, probability, and impact. Risk IDs 2 and 6 have now been realized. Which of the following is the NEXT appropriate step for the project manager to take?
A) Identify risk strategies for the realized events
B) Change the risk status to closed for 2 and 6
C) Consult the risk management plan
D) Update the issue log
Correct Answer:
Verified
Q326: A project sponsor wants to know which
Q327: Which of the following project roles is
Q328: An organization is divided into three separate
Q329: A stakeholder wants to add four more
Q330: A project sponsor approved an undocumented change
Q332: Midway through a project, the building the
Q333: A financial audit is being performed on
Q334: A project team has just finished one
Q335: A project manager is implementing a new
Q336: A project manager is planning to hold
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents