Question 331

Multiple Choice

A project manager has updated the risk register with the current risk status, probability, and impact. Risk IDs 2 and 6 have now been realized. A project manager has updated the risk register with the current risk status, probability, and impact. Risk IDs 2 and 6 have now been realized.   Which of the following is the NEXT appropriate step for the project manager to take? A)  Identify risk strategies for the realized events B)  Change the risk status to closed for 2 and 6 C)  Consult the risk management plan D)  Update the issue log Which of the following is the NEXT appropriate step for the project manager to take?


A) Identify risk strategies for the realized events
B) Change the risk status to closed for 2 and 6
C) Consult the risk management plan
D) Update the issue log

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents