A project manager is performing resource leveling and notices one of the functional testers is assigned 40% in a second project. The project manager needs the resource to be 100% dedicated to the project; otherwise, the testing phase jeopardizes the delivery date. Which of the following should the project manager do NEXT?
A) Ask the resource manager to deallocate the resource from the second project.
B) Ask the resource manager to assign a new resource with 40% of allocation.
C) Keep the resource 100% allocated in the project, as per the initial plan.
D) Change the resource to 60% of allocation and review the mitigation plan.
Correct Answer:
Verified
Q354: The quarterly financial statement has been released,
Q355: A busy project manager has a diverse
Q356: A project manager is starting a project
Q357: Many questions have arisen regarding a newly
Q358: The stakeholders who are available for the
Q360: A key stakeholder claims to have not
Q361: The project team has identified all the
Q362: A highly skilled project engineer will be
Q363: A vendor is late with product deliverables.
Q364: Which of the following are characteristics of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents