The project team has identified all the tasks needed to create project deliverables and grouped them into work packages covering all project scope. Which of the following should be done NEXT?
A) Identify task relationships.
B) Put the resources on tasks.
C) Set the quality gates.
D) Estimate the work package.
Correct Answer:
Verified
Q356: A project manager is starting a project
Q357: Many questions have arisen regarding a newly
Q358: The stakeholders who are available for the
Q359: A project manager is performing resource leveling
Q360: A key stakeholder claims to have not
Q362: A highly skilled project engineer will be
Q363: A vendor is late with product deliverables.
Q364: Which of the following are characteristics of
Q365: A project sponsor promises the Chief Executive
Q366: A project is running behind schedule. To
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents