A project is running behind schedule. To meet the delivery timelines, the project manager decides to give part of the work to another organization for quicker delivery and to allow the project team to focus on the remaining tasks. This is an example of:
A) crashing.
B) outsourcing.
C) task reassignment.
D) relocation.
Correct Answer:
Verified
Q361: The project team has identified all the
Q362: A highly skilled project engineer will be
Q363: A vendor is late with product deliverables.
Q364: Which of the following are characteristics of
Q365: A project sponsor promises the Chief Executive
Q367: The project manager is running a project
Q368: A member of a CCB notices a
Q369: Which of the following are characteristics of
Q370: Which of the following events would MOST
Q371: The government wants to start a project
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents