An External Customer Has Requested a Modification of the Project

Question 399

Multiple Choice

An external customer has requested a modification of the project scope through an official change request. Which of the following is the appropriate NEXT step?


A) Implement the change.
B) Analyze impacts to the project.
C) Create a new change request.
D) Modify the configuration documentation.

Correct Answer:

verifed

Verified