A project manager is working on a project, which needs to be delivered within six months. The project sponsor has made it known that the six months is non-negotiable and additional funding can be provided, if required. The project is in the fifth month, and testing is ongoing. The project team has identified a major defect that will take up to one month to rectify. Which of the following is the BEST action for the project manager to take to ensure the project finishes as planned?
A) Obtain additional resources to crash the timelines.
B) Continue the project as is and communicate the imminent one-month delay to the sponsor.
C) Fast-track non-critical-path activities.
D) Deliver the products to meet the timelines and create an additional phase to address issues.
Correct Answer:
Verified
Q391: Which of the following project management roles
Q392: A company has been trying to implement
Q393: A solid line is connecting a project
Q394: Which of the following documents is a
Q395: A firm, fixed-price project is on pace
Q397: Which of the following is a risk
Q398: A contract manager is reconciling project invoices
Q399: An external customer has requested a modification
Q400: A project stakeholder approaches the project manager
Q401: A project has just begun, and people
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents