A project team member has completed an assigned task on time. After updating the project schedule, which of the following steps should the project manager take NEXT?
A) Send an updated schedule to the CCB.
B) Send a project status update to the sponsor.
C) Release the team members to the functional manager.
D) Notify the team members to begin successor tasks.
Correct Answer:
Verified
Q380: Which of the following organizational structures uses
Q381: A project team is creating a new
Q382: Which of the following describes the difference
Q383: A project manager was reprimanded for failing
Q384: A functional manager within a project is
Q386: A project manager, who previously worked at
Q387: While starting a new project, management is
Q388: Project B cannot start before Project A
Q389: Project cost control deals with:
A) controlling residual
Q390: Project A is delivering the foundation for
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents