Project A is delivering the foundation for Project B. Construction regulations have changed during Project A, requiring work to be redone in the allocated buffer. Which of the following is the MOST likely impact to Project B?
A) The cost will increase.
B) There will be no impact.
C) The scope will change.
D) The schedule will change.
Correct Answer:
Verified
Q385: A project team member has completed an
Q386: A project manager, who previously worked at
Q387: While starting a new project, management is
Q388: Project B cannot start before Project A
Q389: Project cost control deals with:
A) controlling residual
Q391: Which of the following project management roles
Q392: A company has been trying to implement
Q393: A solid line is connecting a project
Q394: Which of the following documents is a
Q395: A firm, fixed-price project is on pace
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents