A stakeholder informs a project manager that a weekly status report has not been delivered via email, but the monthly status reports were received. Which of the following should the project manager do NEXT?
A) Immediately send the current weekly status report
B) Add email to the distribution list for the weekly status report
C) Remove email from the distribution list for the monthly status report
D) Consult the communications plan and act accordingly
Correct Answer:
Verified
Q508: A project manager detects low performance from
Q509: A project manager has set aside a
Q510: A project manager wishes to track a
Q511: The supervisor asks an engineer to be
Q512: A small company has a successful proof
Q514: Tasks A and B have a duration
Q515: An approved change was implemented. Which of
Q516: A company recently went through a project
Q517: An active project is focused on quality
Q518: During planning, a project coordinator publishes the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents