Question 501
Multiple Choice
A project task has been completed ahead of schedule. Which of the following is the MOST appropriate next step?
Question 502
Multiple Choice
A project manager learns that a key team member is required to work on a different assignment within the next two weeks. In which of the following organizational structures does the project manager work?
Question 503
Multiple Choice
A company just announced all third-party vendors must provide ten cybersecurity resources within six weeks. Which of the following documents should the project manager create LAST?
Question 504
Multiple Choice
A project manager noted there were many possible features that could be incorporated into a project, and the customers wavered about whether to include particular features. Which of the following is the BEST approach to ensure appropriate delivery of the project?
Question 505
Multiple Choice
An American publisher is participating in a workshop in Hong Kong with the purpose of updating a new book that will be launched in Japan next year. During the workshop, a deep and intense discussion occurs with other local publishers regarding the references the book may contain. Which of the following BEST describes the situation?
Question 506
Multiple Choice
A project sponsor is reviewing the project dashboard and does not understand what a CPI of 0.87 and an SPI of 1.02 indicate. Which of the following describes the project status?
Question 507
Multiple Choice
Analogous estimating was used earlier in a hauling project; however, through progressive elaboration, it is determined that the cost for fuel is much lower than anticipated. Which of the following types of project change should be submitted?
Question 508
Multiple Choice
A project manager detects low performance from a team member who previously demonstrated to be a highly skilled asset. The team member explains that being part of two teams is too time consuming. This is a disadvantage of having:
Question 509
Multiple Choice
A project manager has set aside a contingency reserve for unforeseen communications. Which of the following types of communication is MOST likely to utilize this contingency reserve?
Question 510
Multiple Choice
A project manager wishes to track a project's performance against the original approved schedule. Which of the following steps is necessary to capture the needed information?
Question 511
Multiple Choice
The supervisor asks an engineer to be a project manager within the department. Of which of the following types of organizational structures is this an example?
Question 512
Multiple Choice
A small company has a successful proof of concept for an innovative new service but lacks the necessary expertise to deploy it. Which of the following is the BEST course of action to address this deficiency?
Question 513
Multiple Choice
A stakeholder informs a project manager that a weekly status report has not been delivered via email, but the monthly status reports were received. Which of the following should the project manager do NEXT?
Question 514
Multiple Choice
Tasks A and B have a duration of two days. Task A starts on Day 1, and Task B starts on Day 3. Tasks C and D have a duration of three days, and Task E has a duration of four days. Task C starts after Task A. Task D and E start after Task C. If Task A starts on December 15, which of the following is the anticipated start date for Task D?
Question 515
Multiple Choice
An approved change was implemented. Which of the following should be accomplished NEXT?
Question 516
Multiple Choice
A company recently went through a project requiring new equipment, new software, and retraining of personnel. This is MOST likely a result of:
Question 517
Multiple Choice
An active project is focused on quality assurance of the deliverable product. In which of the following project phases would this occur?
Question 518
Multiple Choice
During planning, a project coordinator publishes the project management plan. After reviewing the plan, the project sponsor is concerned it is too long and detailed. Which of the following does the project sponsor desire?
Question 519
Multiple Choice
Company A and Company B have come together to form a new Company C. Staff members from both companies have been moved to Company C, and there are rumors that some staff might be asked to leave. These are examples of: (Choose two.)