Question 501
Multiple Choice
A project task has been completed ahead of schedule. Which of the following is the MOST appropriate next step?
Question 502
Multiple Choice
A project manager learns that a key team member is required to work on a different assignment within the next two weeks. In which of the following organizational structures does the project manager work?
Question 503
Multiple Choice
A company just announced all third-party vendors must provide ten cybersecurity resources within six weeks. Which of the following documents should the project manager create LAST?
Question 504
Multiple Choice
A project manager noted there were many possible features that could be incorporated into a project, and the customers wavered about whether to include particular features. Which of the following is the BEST approach to ensure appropriate delivery of the project?
Question 505
Multiple Choice
An American publisher is participating in a workshop in Hong Kong with the purpose of updating a new book that will be launched in Japan next year. During the workshop, a deep and intense discussion occurs with other local publishers regarding the references the book may contain. Which of the following BEST describes the situation?
Question 506
Multiple Choice
A project sponsor is reviewing the project dashboard and does not understand what a CPI of 0.87 and an SPI of 1.02 indicate. Which of the following describes the project status?
Question 507
Multiple Choice
Analogous estimating was used earlier in a hauling project; however, through progressive elaboration, it is determined that the cost for fuel is much lower than anticipated. Which of the following types of project change should be submitted?
Question 508
Multiple Choice
A project manager detects low performance from a team member who previously demonstrated to be a highly skilled asset. The team member explains that being part of two teams is too time consuming. This is a disadvantage of having: