Question 521
Multiple Choice
A project manager is determining a project's critical path to report the projected completion date to stakeholders. Which of the following information will be required? (Select two.)
Question 522
Multiple Choice
A company recently discovered that it could save money by moving its call center to another country. The company entered into an agreement for call center services. Which of the following types of organizational change is this?
Question 523
Multiple Choice
A project team is spread between two countries on different continents. Which of the following factors are MOST likely to influence communication methods selected for the communication plan? (Select TWO) .
Question 524
Multiple Choice
A project team is not delivering their tasks in a timely manner. Additionally, tasks are being reworked because requirements continue to be identified as work packages are being delivered. Which of the following are NOST likely missing from the project? (Select two.)
Question 525
Multiple Choice
While working on risk ranking, the project team is unsure about the qualitative scales to be used for probability and impact. The project manager directs the team to look in the:
Question 526
Multiple Choice
During the planning phase of a construction project, the project team discovers the site is the nesting area birds, and construction could disrupt the bird's patterns. Lobbyists would like the team to move the project down the road. Which of the following constraint and influencer types are involved in this scenario?
Question 527
Multiple Choice
Project status meetings have poor attendance. A SME from the hardware team dominates the meetings when questions are asked, not allowing input from other members. Which of the following steps should the PM take to make the meetings more productive? (Select two.)
Question 528
Multiple Choice
During the planning phase, the project manager meets with the project team to determine the tasks team to determine the task and their relationship. Which of the following should the project manager receive from the team members? (Select two.)
Question 529
Multiple Choice
A diagram or chart is required to illustrate data differences given the following: 1. The diagram or chart must track at least two variables to determine the relationship between independent variables and include a regression or trend line. 2. The diagram or chart should include cause effect analysis and investigate historical information. Which of the following should be used given these requirements?
Question 530
Multiple Choice
A project manager wants to introduce the practice of a WBS to the PMO, but the other managers believe this will create extra work. Which of the following would BEST communicate the need for a WBS to the other managers? (Select TWO) .