A project is coming to the end of a phase. The PMO required that the quality team review the work and budget before moving on to the next phase of the project. The project manager must schedule the review of the phase and have the stakeholders present. This review is referred to as:
A) change management.
B) a milestone.
C) a tollgate.
D) an incident response.
Correct Answer:
Verified
Q530: A project manager wants to introduce the
Q531: Despite receiving regular updates, a sponsor learns
Q532: Which of the following is a characteristic
Q533: A meeting has taken place with quality
Q534: A project manager is analyzing the cost
Q535: Which of the following are the BEST
Q537: Which of the following are mutually binding
Q538: A project team is composed of numerous
Q539: A vendor was removed from a company
Q540: A key team member found a new
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents