During the planning phase of a construction project, the project team discovers the site is the nesting area birds, and construction could disrupt the bird's patterns. Lobbyists would like the team to move the project down the road. Which of the following constraint and influencer types are involved in this scenario?
A) Environmental; resources
B) Environmental; stakeholders
C) Deliverables; resources
D) Deliverables; stakeholders
Correct Answer:
Verified
Q521: A project manager is determining a project's
Q522: A company recently discovered that it could
Q523: A project team is spread between two
Q524: A project team is not delivering their
Q525: While working on risk ranking, the project
Q527: Project status meetings have poor attendance. A
Q528: During the planning phase, the project manager
Q529: A diagram or chart is required to
Q530: A project manager wants to introduce the
Q531: Despite receiving regular updates, a sponsor learns
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents