Solved

Fred Is the Project Manager of the PKL Project

Question 11

Multiple Choice

Fred is the project manager of the PKL project. He is working with his project team to complete the quantitative risk analysis process as a part of risk management planning. Fred understands that once the quantitative risk analysis process is complete, the process will need to be completed again in at least two other times in the project. When will the quantitative risk analysis process need to be repeated?


A) Quantitative risk analysis process will be completed again after the plan risk response planning and as part of procurement.
B) Quantitative risk analysis process will be completed again after the cost management planning and as a part of monitoring and controlling.
C) Quantitative risk analysis process will be completed again after new risks are identified and as part of monitoring and controlling.
D) Quantitative risk analysis process will be completed again after the risk response planning and as a part of monitoring and controlling.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents