The Only Output of the Perform Qualitative Risk Analysis Are

Question 8

Multiple Choice

The only output of the perform qualitative risk analysis are risk register updates. When the project manager updates the risk register he will need to include several pieces of information including all of the following except for which one?


A) Trends in qualitative risk analysis
B) Risk probability-impact matrix
C) Watchlist of low-priority risks
D) Risks grouped by categories

Correct Answer: