Mary is the project manager of the HGH Project for her company. She and her project team have agreed that if the vendor is late by more than ten days they will cancel the order and hire the NBG Company to fulfill the order. The NBG Company can guarantee orders within three days, but the costs of their products are significantly more expensive than the current vendor. What type of a response strategy is this?
A) External risk response
B) Internal risk management strategy
C) Contingent response strategy
D) Expert judgment
Correct Answer:
Verified
Q1: In which type of access control do
Q2: Which of the following parts of BS
Q3: Which of the following are included in
Q4: Henry is the project manager of the
Q6: Which of the following NIST Special Publication
Q7: The Phase 1 of DITSCAP C&A is
Q8: The only output of the perform qualitative
Q9: Shoulder surfing is a type of in-person
Q10: Which of the following formulas was developed
Q11: Fred is the project manager of the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents