You are the project manager of the NNH Project. In this project you have created a contingency response that the schedule performance index should be less than 0.93. The NHH Project has a budget at completion of $945,000 and is 45 percent complete though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone. What is the project's schedule performance index?
A) 1.06
B) 0.93
C) -$37,800
D) 0.92
Correct Answer:
Verified
Q135: Which of the following is a temporary
Q136: You are working as a project manager
Q137: Which of the following processes is described
Q138: Which of the following is a 1996
Q139: Jenny is the project manager for the
Q141: Which of the following documents is described
Q142: Thomas is a key stakeholder in your
Q143: To help review or design security controls,
Q144: Which of the following access control models
Q145: Which of the following components ensures that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents