Your organization has named you the project manager of the JKN Project. This project has a BAC of $1,500,000 and it is expected to last 18 months. Management has agreed that if the schedule baseline has a variance of more than five percent then you will need to crash the project. What happens when the project manager crashes a project?
A) Project costs will increase.
B) The amount of hours a resource can be used will diminish.
C) The project will take longer to complete, but risks will diminish.
D) Project risks will increase.
Correct Answer:
Verified
Q158: Amy is the project manager for her
Q159: Information Security management is a process of
Q160: Walter is the project manager of a
Q161: A security policy is an overall general
Q162: System Authorization is the risk management process.
Q164: Which of the following DoD directives defines
Q165: Which of the following is NOT an
Q166: Fred is the project manager of the
Q167: Which of the following are the common
Q168: You are the project manager of the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents